Issue - meetings

Crematorium South Chapel Refurbishment

Meeting: 15/09/2014 - Portchester Crematorium Joint Committee (Item 600)

Crematorium South Chapel Refurbishment

Under minute 585 at the meeting held on 16 June 2014, the Joint Committee received a presentation and briefing on a scheme for the refurbishment of the interior of the South Chapel.

 

The Engineer and Surveyor will update members.

 

RECOMMENDED that the Engineer and Surveyor’s verbal report be received.

Minutes:

The Deputy Engineer and Surveyor updated members regarding the refurbishment works approved under minute 585.

 

The Joint Committee was shown samples of the types of wood wall covering and fixing arrangements proposed by Robert Benn Associates, as illustrated on the plans prepared by RBA and displayed at the meeting.   

 

Members indicated they wished to see light coloured American Yellow Poplar used, and that the panel sections be fixed vertically to the walls.

 

Members were advised that the work’s programme envisaged tenders being invited during November 2014 with out of hours on site work being undertaken during the spring 2015.

 

The officers would be overseeing and progressing the project and reporting to the Joint Committee.     However it was suggested that if and when there were any material design or related issues arising that required immediate resolution they would consult with the chairman, and members agreed this course of action.

 

RESOLVED (1) that light coloured American Yellow Poplar wood be used for the wall coverings and that the panel sections be affixed vertically to the walls.  

 

(2) that it be noted that the Engineer and Surveyor will be overseeing and progressing the project and if and when there are any material design or related issues arising that require immediate resolution a decision be taken after consultation with the Chairman.