Solent Connectivity: the Network Rail Solent modular strategic plan

Meeting: 29/10/2020 - Cabinet Member for Traffic & Transportation (Item 32)

32 Solent Connectivity: the Network Rail Solent Continuous Modular Strategy Plan pdf icon PDF 676 KB

Purpose.

The purpose of this report is to inform members of the recommendations for the future development of train services in the Solent area (Portsmouth – Southampton/Eastleigh) contained in “Solent Connectivity”, the Solent Continuous Modular Strategic Planning (CMSP) study

 

RECOMMENDATIONS

It is recommended that the Cabinet Member for Traffic and Transportation:

 

1.    Notes the contents of this report

2.    Endorses the CMSP recommended train service specification:

·         Portsmouth – Southampton: additional 2 trains per hour giving 4 trains per hour; and

·         Portsmouth – Eastleigh: additional train per hour giving 2 trains per hour.

 

3.    Supports in principle the following CMSP recommended infrastructure measures that will be required in Portsmouth to facilitate the new services:

·         Reinstatement of track in platform 2 at Portsmouth Harbour station, bringing the platform back into use; and/or

·         Provision of an additional platform at Portsmouth and Southsea station, adjacent to the low-level platforms 3 and 4.

 

 

 

 

Additional documents:

Decision:

1.    Noted the contents of this report

2.    Endorsed the CMSP recommended train service specification:

  • Portsmouth Southampton: additional 2 trains per hour giving 4 trains per hour; and
  • Portsmouth Eastleigh: additional train per hour giving 2 trains per hour.

3.    Supported in principle the following CMSP recommended infrastructure measures that will be required in Portsmouth to facilitate the new services:

  • Agreed the reinstatement of track in platform 2 at Portsmouth Harbour station, bringing the platform back into use; and/or
  • Agreed the provision of an additional platform at Portsmouth and Southsea station, adjacent to the low-level platforms 3 and 4.

 

Minutes:

Hayley Chivers, Strategic Transport Leadintroduced the report and with James Nevell, Public Transport Officer in response to questions from members clarified the following points:

 

After the pandemic, more information on travel demand patterns will be available and the options will be reassessed. 

·           New infrastructure will be required to facilitate the proposed service improvements.

·           More terminal capacity will also mean more robust train timetables and better punctuality.

·           Solent Transport is working with the Department for Transport and Network Rail to secure inclusion of the necessary infrastructure measures in the Rail Network Enhancement Programme.

·           The detailed modelling is yet to be done.

 

DECISIONS

1.     Noted the contents of this report

2.     Endorsed the CMSP recommended train service specification:

·           Portsmouth Southampton: additional 2 trains per hour giving 4 trains per hour; and

·           Portsmouth Eastleigh: additional train per hour giving 2 trains per hour.

3.     Supported in principle the following CMSP recommended infrastructure measures that will be required in Portsmouth to facilitate the new services:

·           Agreed the reinstatement of track in platform 2 at Portsmouth Harbour station, bringing the platform back into use; and/or

·           Agreed the provision of an additional platform at Portsmouth and Southsea station, adjacent to the low-level platforms 3 and 4.