7. Greening the City Update PDF 243 KB
The purpose of the report by the Assistant Director of Planning and Economic Growth is to update Members on the progress that has been made on the 2018-19 Green Infrastructure delivery plan project. Six months on from the approval of the plan, it is a good time to provide an update on the progress that has been made with this project, and set out the further planned
work that is in place to be taken forward over the remainder of the year. A
number of proposals are also made with respect to how the project should
progress in relation to several new opportunities that have been identified.
RECOMMENDED that Cabinet:
(1) Note the progress and ongoing work as set out in this report.
(2) Endorse the proposals set out in the appendix project update summary table.
Additional documents: