Quarterly Update on the School Modernisation programme 2017/18

Meeting: 15/02/2018 - Cabinet Member for Education (Item 11)

11 Quarterly Update on the School Modernisation programme 2017/18 pdf icon PDF 126 KB

Purpose of report

 

1.1                   The purpose of this report is to provide a Quarter 3 update on the progress of:

 

·                     urgent school condition projects

·                     secondary school sufficiency schemes aimed at increasing secondary school place capacity within the city.

 

1.2       The quarterly budget monitoring report (also on this agenda) contains information in relation the financial position of the education capital programme.

 

 

RECOMMENDEDthat the Cabinet Member notes the progress on the school modernisation "urgent condition" projects and the secondary school sufficiency projects (as set out in the report and in Appendix A).

 

Additional documents:

Minutes:

(TAKE IN REPORT)

The report was introduced by Caroline Corcoran, Head of Sufficiency, Participation and Resources.  She explained that there have been no new works that were required since the last report and seven of the urgent condition projects had been completed.   

 

In response to a question from the Cabinet Member, Ms Corcoran said that there were no new or emerging risks.

 

DECISION: The Cabinet Member noted the progress on the school modernisation "urgent condition" projects and the secondary school sufficiency projects (as set out in the report and in Appendix A).