The City Council's Response to the Aquind Proposal

Decision Maker: Cabinet

Is Key decision?: Yes

Is subject to call in?: No

Decision:

DECISIONS

The Cabinet:

1.    Noted that Aquind are seeking to develop an electricity Interconnector between the UK and France with a converter station in Lovedean.  They are proposing to "land" the high voltage DC (HVDC) electricity cable at Eastney and run it up through Portsmouth to the converter station at Lovedean.

 

2.    Noted that despite representations from Portsmouth City Council that the Aquind proposal should be determined by the relevant local planning authorities (including Portsmouth City Council), the Government has decided that the proposal was a 'Nationally Significant Infrastructure Project' that should be determined by the Secretary of State through the Development Consent Order process.

 

3.    Agreed to seek the support of Full Council to reinforce the Cabinet's objection to the route of the HVDC cable whilst also working constructively with Aquind and other stakeholders.

 

4.    Agreed that the Council responds to this proposal in a coordinated way and where possible works with neighbouring councils on any common approaches.

 

5.  Noted that any additional external costs incurred in the current year associated with the need to make an informed and considered response to the proposal will be met from the Council's Corporate Contingency.

Report author: Kelly Nash

Publication date: 10/07/2019

Date of decision: 09/07/2019

Decided at meeting: 09/07/2019 - Cabinet